Monday, September 6, 2010

Mondays Metting

Date
6/9/10
Absent
No one
Agendas raised
·         Time to start on the technical menu
·         Look to have the user manual 70 to 80 percent complete by the end of the week
Things to look into further
Nothing for the time being
What should be done by next meeting
·      The user manual should be around 70 to 80 percent complete by the next time we meet
·      Phil and Jun should be moving along with their examples, not finished but comfortably on their way to a complete example
Tasks assigned to individual users
Phill and Jun are still working on their examples of possible ways to model the main part of our program
Allen – is going to look out the program from a hierarchial view. This means the layout of the whole program and possible ways to orgainised different classes
Jernej – is looking into common knots. This common knots are what we hope to try and model within our program. He will gain a full understanding of these knots and the steps required to construct these knots.
Tim – will add all the user interface stuff to the user manual. This includes the interface created by Jun and all the functionality related to it
Tasks completed
·         Everyone is happy how the user interface looks and the menu system behind it
·          
Summary
Overall this was a fairly brief meeting because of the direction we take from here depends on which example from Phil and Jun is best for us to implement and continue with.

Everyone is happy with the way the user interface looks and will work in relation to the user. The interface is simple and visually pleasing to any regular windows user. It isn’t over powering and is very basic but gives the user the options they would need to be able to complete a knot

No comments:

Post a Comment