| Date | 12/1/11 |
| Away | - |
| Agendas Raised | · What progress has been made · What people have been doing since we last spoke |
| Tasks assigned | Tim · Continue to help where needed and work on the documentation Phil · Has finished the basis of the viewports now just needs to tidy up the code to make it more readable and understandable Jernej · Looking into methods of testing for when the testing stage will begin Jun · Continuing to work on the manipulation of the knot Allen · Working in tangent with Jun to store the knots within a possible database |
| Summary | This was our first group meeting in over month due to people being on holidays, festive season and others having work commitments. This meeting was mainly about what progress had been made since we last had a group meeting. Things seem to be moving along nicely and we should be close to a prototype stage by the time we get back to uni. Some ideas and concerns were raised and discussed as a group. These ideas were in relation to how things and events could be handled. Phil had an idea that sounds tricky to implement but once implemented makes other tasks easier. |
Thursday, January 13, 2011
Subscribe to:
Post Comments (Atom)
No comments:
Post a Comment